Phase II

Approximate Time Frame – Nov. 15, 2003 To Dec. 31 2004

1. Improve Foundations Under Building As Required

2. Refurbish Floor Supports As Required

3. Commence Interior Finishes

4. Begin Staining and Painting Woodwork

5. Begin Hand Painted Walls and Ceiling in Chancel

6. Begin Mechanical Work (Heating, Plumbing, Sprinkler, Ventilation)

7. Begin Electrical Work (Main Entrance, Wiring, Lighting, Security System)

8. Begin Mural Work

9. Begin Repair and Restoration of Pews

10. Complete Washrooms, Changing Rooms, Vestry, Sacristy